A SAGE Group Company

24/7 Support: 1800 724 373

Control system engineering works have ensured treated wastewater will safely supply southern homes...  

Industry

Utilities: Water

Outcome

SAGE completed control system works on key infrastructural assets to allow the waste water storage and treatment plant to function. 

Capability
RTU, SCADA, HMI & PLC system design, networking, programming & integration, control panel manufacture & wiring, Factory & Site Acceptance Testing
Region

 Multiple locations, South Australia

Challenge

The $62.6 million Southern Urban Reuse Project (SURP) is jointly funded by the SA and Federal Governments. It forms one element of the ‘Water Proofing the South’ strategy being led by the City of Onkaparinga.

Each year 1.6 billion litres of treated wastewater will be transferred from the Christies Beach Wastewater Treatment Plant to the Aldinga Wastewater Treatment Plant where it will be stored.

The wastewater will then be further treated before being provided to up to 8000 new homes in the south for use in dual reticulation systems, including toilet flushing and garden watering.

Solution

SAGE was engaged by LEED Engineering and Guidera O'Connor to complete works associated with four key areas of the project. These include: the Christies Beach Main Control Cubicle, Aldinga Pumping Station, Aldinga Water Farm Pump Stations and Hypo building, and the SURP Main Control Panels.

 The solution included:

  • Project Management
  • Estimation, cost planning and procurement
  • Risk mitigation planning and management
  • CAD drafting and low/medium voltage electrical design and commissioning
  • RTU, SCADA, HMI and PLC system design, networking, programming abd integration
  • Control panel manufacture and wiring
  • Factory and Site Acceptance Testing
  • Project Management
  • RTU Installation & commissioning
  • Provision of final, as built, documentation

Outcome

Working with multiple Lead Contractors and under challenging timeframes, SAGE allocated large Engineering, CAD and workshop resources to the project and has since been awarded further work with these lead contractors.

Key deliverables for each key area:

  • Christies Beach Main Control Cubicle - SAGE built the Main Control Cubicle (MCC) for the pumping station which features variable speed drives and PLC controls. This project included CAD design, PLC programming and commissioning of the station with RTU connection to the Metro Telemetry System
  • Aldinga Pumping Station - this element of the project included CAD design, PLC programming and commissioning and connection of the Pumping Station to the Aldinga Water Farm via Elpro radios
  • Aldinga Water Farm pump stations and Hypo building (dosing)
  • SURP Control Panels - including CAD design, control panel construction, PLC and SCADA design as well as construction and commissioning of the screens.

Technology Used:

  • SCADA: iFIX
  • PLC/SLCs: Redundant Allen Bradley ControlLogix system
  • RTU: Kingfisher & Logica
  • Radios: Elpro & Trio
  • HMI: Allen Bradley
  • Variable Speed Drives: Allen Bradley & ABB
  • Networks: Devicenet, Ethernet, Control, Profibus

Talk to us about...